HGC Estimate to complete Spring 2025
TTU Draft:
CMU Draft:
- https://docs.google.com/document/d/1msi-dcXXjjYUP_KDZWxZuBitXJ19NpzQ/edit
- DocDB: CMU https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=14209
UCSB Draft:
Bottom-up Labor:
Logs
2 April 2025 Wednesday
- HGC MAC BoEs
- Update UCSB bottom-up labor estimate :
- Update doc file.
- Posted to docDB
1 April 2025 Tuesday
- DocDB: CMU https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=14209
- [>>] Source Spreadsheet for UCSB
- [>>] ETC for Module Factories
25 March 2025 Tuesday
- Starting CMU doc:
- https://docs.google.com/document/d/1msi-dcXXjjYUP_KDZWxZuBitXJ19NpzQ/edit
- Worked out EAC… basically all assembly
- [>>] Need to understand CPI
- Starting UCSB
- https://docs.google.com/document/d/1Lq3zZo9QBQr_rVQb1P93QetfB1_aQH9O/edit
- 90k for undergrad vs 9k at CMU and TTU ?
- Read BoE HGC MAC BoEs
- Partials: Top / Bottom / Left / Right / Five
- [>>] Need to understand CPI
24 March 2025 Monday
- Understood Steve numbers
- drafted section
- pinged Nural
19 March 2025 Wednesday
- Moved bottom-up estimate to google sheets:
- https://docs.google.com/spreadsheets/d/12ihDV7ayNyCY-qErWg072wRIgj5y4M97oYKE2SUkcP4/edit?gid=1242185869#gid=1242185869
18 March 2025 Tuesday
- https://docs.google.com/document/d/1Zr5eGtIJggx2pvEH6K-42vE-SKYvYxTc/edit
- From Steve's mail:
- 2) Are the resource-loaded schedule and the estimate-to-complete up-to-date, accurate and credible?
- 6) Has the risk analysis been updated to reflect the real risks of completing the project and are the contingencies acceptable?
- Slides: https://cms-docdb.cern.ch/cgi-bin/DocDB/RetrieveFile?docid=14209&filename=CE-CD3-IPR_Nov2023_Drilldown_Paulini_402_4_4_4.pdf&version=8
- DocDB: https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=14209
Standard module assembly site 2 (CMU) produces, tests, and delivers about 4240 HGC standard (low- density) modules to US cassette assembly site at Fermilab
- HGC MAC BoEs
- Total cost $1,776k for CR Standard Module Assembly Site 2 ($207k uncertainty from 17.5% on Labor for techs)
- Dominated by labor 95% $188k
- FTES:
- Senior Engineer (Jessica) + 4 techs (Ornella + Jonas + Josh +
____) + 2 students
- Senior Engineer (Jessica) + 4 techs (Ornella + Jonas + Josh +
- Schedule HGC week: https://indico.cern.ch/event/1464337/contributions/6165029/attachments/3015759/5320011/20250217_Intro_Overview.pdf
- Has modules finishing in Oct 2026
- Workforce Preparation for the Module Assembly
- Rates: (From Vars)
- 1-80:
- Tech 1 (Jr ) : 28k
- Tech 3(senior): 13k
- UG: 8k
- Engineer 20k
- 81-240
- Tech 1 (Jr ) : 28k (1-80): 56k
- Tech 3(senior): 26k
- UG: 16k
- Engineer: 40k
- 8%-block;
- Tech 1 (Jr ) : 41k
- Tech 3(senior): 19k
- UG: 12k
- Engineer: 28k
- 1-80: